Status Update - 3/28/19
	    March 28, 2019
	
    | Status Item | Current Status | Previous Status | Comment | 
| Schedule | green | green | |
| Resources | green | green | No resource availability issues | 
| Financials | green | green | CO for $31,180 fully executed | 
| Quality | green | green | Quality metric remains green | 
| Project Issues | yellow | yellow | Banner/Axiom Integration data load is delayed | 
| Key Deliverables | % | Comments | Timeline | 
| Requirement Sign-off | 100% | 12/14 | |
| Data Model/Mapping | 100% | 1/12 | |
| Build | 99% | Last full sprint | 3/29 | 
| Integration | 6% | Terms have been loaded in UAT | 3/29 | 
| Training/UAT | 0% | Training and UAT dates delayed | 4/22 | 
For the detailed March 28, 2019 status report, click here.